top of page
  • Writer's pictureChelsea Biehl

Letter to the Editor

Attention: Gregory County Pumped Storage Project Stakeholders (Landowners, Businesses,

Personal and Taxpayers)


*Missouri River Energy and MidAmerican Energy Company have been trying real hard to

pull the wool over our eyes. But here are a few things they don’t want you to know about

this project.


*It is an “out of state, private, for profit company” coming to SD and taking our beautiful,

productive land by eminent domain for private gain by generating power to sell to the

highest out of state bidder. There is nothing good here for Chas. Mix or Gregory Co. God

gave us this beautiful land, please do not destroy it because of greed!


*Wonder where your income tax money is going? Up to 3 Billion of our tax money will go to

pay for Gregory Co. Pumped Storage Project.


And more tax bologna…The Gregory County Commissioners were given estimates of tax

revenue Gregory Co and the Burke School District will receive from this project. The SD



Dept. of Revenue has stated they do not know how much it will be taxed until construction

has started. And since when do these out of state companies get to decide how much we

are going to pay in taxes. Not a very trustworthy company if they think they know more

than SD Dept. of Revenue and our own county.


*Oh Yes, they told us they cut the reservoir by approx. 1/2, down to 1125 acres. (This is the

3rd plan change


they’ve thrown at us since last April) What they didn’t tell you, is now to

generate the power they have to have for their plan, they have to have the water go up and

down the tunnels and through the turbines 2.5X’s more. Therefore, 2.5X’s the amount of

turbulence, 2.5X’s the amount of vibration, and 2.5 X’s the amount of sediment and sand

movement. Less time for it to settle. Quicker erosion of the shoreline.


*With this project, the entire 107 miles of Lake Francis Case is pumped up and released 2X’s

per year. That’s a lot of water being pumped out of the Missouri River! In other areas of SD

some hydroplants are not working because the Missouri River is too low. The question???

Why would it work here? Gregory County Pumped Storage Project will consume more

energy than the Oahe Dam and Ft. Randall Dam produced together.




Please help stop these out of state companies from invading our peaceful community.

Susan Chytka

24 views0 comments
bottom of page